1. Home
  2. Why we pour and pump
One crew, both jobs

One crew forms it, pours it and pumps it

Most concrete crews own forms, floats and a truck. The pump is the one piece they have to go find. We own ours, so when a job needs concrete placed where the mixer truck cannot reach, there is no third company to schedule and nobody to point at if it does not show up. One crew, start to finish.

The Bowman Griffin concrete pump rig and truck

How a pumped pour normally comes together

Here is the way it usually works, and there is nothing wrong with the people doing it. A builder or a homeowner hires a concrete crew. The crew walks the site, sees a backyard slab behind a gate or a foundation stepped down a grade, and knows the mixer truck is never going to reach the forms. So they book a pump from an outfit that has one. Now the job has three calendars on it instead of one.

Those three are the concrete crew, the ready-mix plant and the pump outfit. All three have to land on the same morning, in the same weather window, in the right order. The plant is scheduling trucks for everybody in the county that day. The pump outfit is doing the same with its equipment. Most of the time it works out. When it does not, it does not fail quietly.

On our jobs that middle calendar does not exist. The pump belongs to us, so booking a pour means getting two parties to agree instead of three: our own crew and the ready-mix plant. That is the whole list.

What goes wrong when the pump is the loose piece

Concrete has a clock in it. Once the plant loads the first truck, everybody standing on that site is working against that clock, and it does not pause for a phone call. That is what makes a late pump different from a late anything else.

If the outside pump runs an hour behind, the trucks are still coming, and concrete sitting in a driveway is getting older by the minute. If the pump does not show at all, the pour gets scrubbed. The load gets canceled, the crew stands down, and everybody reschedules around whatever the weather does next week. On a footing already dug open, that is not a small thing.

There is also the question of who is standing there when it happens. The crew that showed up on time is the one in your driveway explaining a delay it did not cause, and there is nobody on site with the ability to fix it. That conversation is nobody's fault and it is still your morning.

The other way it goes sideways is quieter. The pump shows up, but the man running it has never worked with that crew, does not know the mix that was ordered, and is putting line together on a site he has never seen. Concrete comes in surges instead of steady, the finishers fall behind, and the surface pays for it.

Take the outside pump out of the picture and none of that is on the table.

The pumping is part of the price, not a pass-through

When a crew has to bring in a pump, that cost reaches you as a pass-through with a markup on it, and the crew has little say in what it costs them. That is not sharp practice. It is what happens when the equipment belongs to somebody else.

We price the pump into the job. On our own pours the whole thing lands on a single written estimate from a single crew: forming, sub-base, steel, placing, pumping, finishing and cleanup. There is no separate pumping line to chase down and no second company to pay.

It also means we can tell you the truth about whether you need it. We would rather chute it straight off the truck when the truck can reach, because that is faster and cheaper for everybody standing there. When we say a pour needs the pump, it is because it does, and it is written on your free estimate before anybody starts work.

One crew, one name on the work

Split a pour between two companies and you have built a seam into the job. Seams are where the arguments happen.

If a slab comes out with a bad surface, was that the finish or the placement? If a wall got a cold joint in it, was that the crew or the line running dry? When two companies were on site, both of those questions have two answers and you are the one who gets to sort them out. When it is one crew, there is nothing to sort out. Our operator, our hose guy, our finishers, our name on the estimate.

It shows up in how the pour runs, too. The man on the hose and the men on the screed work together every week, so he knows how fast they want it and where. A steady pour is easier to finish than a stop-and-start one.

The finished work carries a workmanship warranty, terms confirmed on the written estimate.

The machine itself, and where the rest of it is written down

None of the above means much without saying what the equipment actually is, so here it is short. We own one trailer-mounted line pump. It gets towed to the job, parked on solid ground, and moves concrete down hose, 2.5 inch and 3 inch, that two of our people walk out to the forms. Access and yardage decide whether your pour wants it, and we settle that when we look at the site, not on pour morning. The long version, what the rig reaches, what it will not do, and which pours call for one, is written out on our pump page.

Builders and crews with their own men on the forms can put us on a date too. You hire Bowman Griffin for the placing and our people come out and do it. Nobody outside this company runs that machine, ever, so what you are booking is a crew with a pump, not a pump by itself. What we need from you beforehand and how we work around your ready-mix window are laid out on our page for builders and contractors.

Good questions

Why does it matter who owns the concrete pump?

Because it decides how many companies have to agree on one morning. When the crew owns the pump, your pour needs the crew and the ready-mix plant to line up, and that is all. When the pump comes from somewhere else, a third schedule has to fit too, and it is the one piece nobody on the job can move.

Do I pay extra for the pumping if you pour my job?

The pumping is priced into the job, not added on as another company's bill with a markup on top. One estimate in writing covers form work, placing, pumping and finish. If your pour does not need the pump at all, we chute it off the truck and it is not in the number.

How do I know whether my pour needs a pump?

Usually access and yardage settle it in about two minutes on the phone. Foundations, pours of roughly 8 cubic yards or more, backyards behind a gate, basements, and any site where the truck cannot get near the forms are the common ones. We come out and look before we say either way.

Rain moves my pour. What happens to the schedule then?

It moves with us, and there is nothing to renegotiate. Our crew picks up a new date with the plant and the pump comes along, because it is parked in our yard either way. When a pour is split between two companies, a weather day means hunting for a morning that suits both of them again, and that hunt is usually longer than the rain was.

If a question comes up after the pour, who am I calling?

The same number you called to book it. One crew formed it, placed it and finished it, so there is no second company to route the question through and no argument about which half of the work it came out of. The workmanship warranty and its exact terms sit on that same written estimate.

I already have a concrete crew. Can I still get you out?

Yes, for the placing end of it. Your men run the pour and ours run the line, and your customer stays yours. Ring us with the date, the address and roughly how many yards, and we will say what is open on the calendar. The particulars live on our page for builders and contractors.

One crew, one written estimate

Call 276-733-3750 and say what you are pouring and where it has to land. Somebody will walk the site, take the measurements, and tell you straight whether the pump belongs on that job. The written estimate that follows costs you nothing.

Call Free Quote