Yardage and trucks

How many yards of concrete do I need?

The short answer

Multiply length by width by thickness, all in feet, then divide by 27. Four inches is a third of a foot and eight inches is two thirds. Add 10 percent for waste and round up. A 20 by 20 patio at 4 inches comes to 4.9 cubic yards calculated and 5.4 with the waste allowance. Ready mix is ordered in 10 cubic yard loads, and a job rounds up to the next full load.

Measure the two numbers, then decide the third

Two of the three figures are measurements and the third is a decision. Length and width you take with a tape. Thickness gets chosen for what the slab has to carry, and it is the one that moves the volume the most.

Standard flatwork is 4 inches. A garage floor goes to 5. A foundation is poured at 8. Stepping from 4 inches to 5 is 25 percent more concrete before anything else about the job changes, which is why thickness is worth settling before you run the numbers rather than after somebody has already quoted you.

For an odd shape, break it into rectangles, work each one and add them up. A curved patio edge or a clipped corner is close enough if you square it off and take the slightly larger figure, because you are ordering with a waste allowance on top of it anyway.

Feet, then cubic feet, then divide by 27

The arithmetic is short. Get all three numbers into feet, multiply them together, divide by 27. The only step people trip on is the thickness, because it arrives in inches and has to go in as a fraction of a foot.

  • 4 inches is 0.33 of a foot
  • 5 inches is 0.42 of a foot
  • 6 inches is 0.5 of a foot
  • 8 inches is 0.67 of a foot

The same tape measure, two very different volumes

Take a 20 by 20 patio. That is 400 square feet. At 4 inches it is 400 times 0.33, or 133 cubic feet, and 133 divided by 27 is 4.9 cubic yards.

Pour that identical 400 square feet at 8 inches instead and it is 268 cubic feet, or 9.9 cubic yards. Twice the concrete off the same tape measure, which is the reason a volume figure quoted without a thickness beside it does not tell anybody anything.

So when you compare your number against somebody else's, check that both were figured at the same thickness before you decide one of them is wrong.

Add the 10 percent before you call anybody

Order 10 percent over the calculated volume. The 4.9 yard patio above becomes 5.4.

That allowance is not padding. Forms flex outward under the weight of wet concrete, the subgrade is never perfectly flat no matter how well it was graded, and some concrete always stays behind in the chute or the line. Ordering the exact calculated figure is how a crew ends up a wheelbarrow short.

Running short is the expensive version of this mistake, because what you get is a cold joint through the middle of a slab that was meant to be one piece, and there is no taking it back once the concrete has stiffened. Running a little long is the cheap version. The extra goes to the washout spot that was agreed on before the pour started.

Where your number lands against a load

Ready mix comes in 10 cubic yard loads and a job rounds up to the next full one. Our page on by the yard versus by the job works through what that does to a pour sitting near the boundary. For your own planning, the useful thing is simply knowing which side of it you are on.

Two other things ride on the yardage. A pour that runs about 8 cubic yards or more is usually a line pump job in our book, along with any foundation and any site where the truck cannot get near the forms. And the volume tells you how much crew has to be standing in the forms when the concrete arrives, because a slab is placed and finished at the rate people can work, not at the rate a truck can empty.

The yardage is not the price

Cubic yards tell you what to order. They do not tell you what the job costs, because the concrete is one line inside a finished slab that also takes layout, excavation, a compacted stone base, forms, reinforcement, placement, finishing and joints cut on schedule.

We price by the installed square foot for exactly that reason. The 400 square foot patio above sits in the patio band of $9 to $14 per square foot installed, which plans out at $3,600 to $5,600. Our cost page carries the rest of the bands by project type, and our page on by the yard versus by the job explains why the two units look so different on paper.

Use cubic yards to sanity check a truck count. Use installed square feet when you are holding two crews' pages side by side.

Good questions

Do I add the 10 percent before or after rounding up to a load?

Before. Calculate the volume, add the 10 percent, then see what load count that lands in. Rounding first and adding waste afterward is how a job ends up ordering concrete it did not need, or short on the load it did.

What happens to concrete I ordered and did not use?

It goes to the washout spot agreed on before the pour started, not into your yard and not into a storm drain. Running a little long is a much smaller problem than running short with forms still open.

Does using the pump change how much concrete I need?

No. The forms hold what the forms hold. The pump changes how the concrete gets from the truck to the forms, not how much of it the slab takes.

How accurate does my measurement have to be?

Close is fine at the planning stage, and the 10 percent covers ordinary slop in a tape measure. Before anybody orders a truck we measure it ourselves on the estimate visit, because the grade cut and the final thickness move the volume as much as the length and width do.

Want your yardage checked before anybody orders a truck?

Call with your length, width and thickness and we will run the volume with you, waste allowance and load count included, at no charge.